LOCATION: Dry Creek Rail Yard

CONTRACT PERIOD: 2 Years

CLIENT: Smart Systems

SERVICE:
Complete the mechanical / hydraulic / electrical design and installation of 10 sets of doors for the state government rail service department premises.

SCOPE:
Torque were approached to provide a solution to a problem; the electrical systems would not work due to the large site wind force calculations. Torque's engineering department designed a system which would provide the safe and simple operation of the doors within the physical restraints of the building.

FEATURES:

  • Electrical design of complete control panels
  • Mechanical design of mounting brackets and cylinders
  • Hydraulic design
  • Power unit design
  • Design piping layout
  • Onsite installation